How Long Does a Kitchen Renovation Take? Stage-by-Stage Timeline

How Long Does a Kitchen Renovation Take

Most homeowners ask the same first question: how long will we be without a kitchen? The honest answer has two parts. The full kitchen renovation timeline runs from the first design meeting to handover, often two to four months. The time your kitchen is out of use is much shorter, usually one to six weeks. Your benchtop, layout and the age of your home decide where you land. This guide breaks the job into eight stages, shows what can overlap and explains what delays Melbourne jobs.

Kitchen Renovation Timeline at a Glance
6 to 12 weeks

Final design to handover

1 to 2 weeks

Kitchen out of use with laminate

3 to 5 weeks

Kitchen out of use with stone

8 stages

From design to handover

Most full kitchen renovations take 6 to 12 weeks from final design to handover. The kitchen is out of use for 1 to 2 weeks with laminate benchtops, or 3 to 5 with stone. Layout changes, structural work and permits stretch both numbers.

So how long do kitchen renovations take for your type of job? Track two clocks: the whole project, and the stretch with no working sink.

Type of jobFinal design to handoverKitchen out of useWhat sets the pace
Same layout, laminate benchtop4 to 8 weeks1 to 2 weeksCabinet manufacture
Same layout, stone benchtop6 to 10 weeks3 to 5 weeksStone templating and cutting
New layout, plumbing or power moved8 to 12 weeks4 to 6 weeksRough-in and trade bookings
Walls removed or structural work12 weeks or more6 weeks or morePermit, engineer and builder

Kitchen renovation timeline by type of job (indicative industry ranges)

These ranges come from published industry guides, not a quote. Your kitchen company should give you a date for every stage.

The Kitchen Renovation Timeline, Stage by Stage

Every kitchen renovation process follows a similar order. Each stage of this kitchen renovation timeline covers what happens, the typical time and what to settle next.

The Kitchen Renovation Timeline, Stage by Stage

1. Design and Selections

Your designer measures the room, plans the layout and helps you choose finishes. Pick appliances, sink and tapware now, because their sizes shape the cabinets.

Typical time: 2 to 6 weeks.

Before you move on: sign off the final drawings and appliance list.

2. Quote, Check Measure and Approvals

The quote is finalised, and the room is measured again against the final design. If walls move, your builder engages a building surveyor and, often, an engineer. Apartment owners may also need owners corporation approval.

Typical time: 1 to 3 weeks, or longer when a permit is needed.

Before you move on: confirm who holds each approval and when it lands.

3. Cabinet Manufacture and Ordering

The workshop cuts, edges and builds your cabinets while your old kitchen still works. Order appliances, sink and tapware now so they arrive before installation.

Typical time: about 1 to 6 weeks across the industry, depending on the maker and the job.

Before you move on: get a confirmed date for the cabinets and appliances.

Cabinet Manufacture and Ordering

4. Demolition and Strip Out

Licensed trades disconnect water, gas and power, then the old kitchen comes out. Homes built before 1990 may contain asbestos, so test first and use a licensed removalist.

Typical time: 1 to 2 days, plus any asbestos removal.

Before you move on: set up your temporary kitchen somewhere else in the house.

5. Rough-In and Wall Repairs

Your plumber and electrician run new pipes, power points and lighting to match the plans. Plasterers then patch the walls. Moving services after the cabinets arrive causes rework.

Typical time: 2 to 5 days.

Before you move on: check every outlet position against the plan.

6. Cabinet Installation

Installers fix fully assembled cabinets in place, level and join them, then fit doors and panels. Flat pack cabinets need assembly first. Kickboards stay off if new flooring is still to go down.

Typical time: 1 to 3 days for assembled cabinets.

Before you move on: book the stone template as soon as the cabinets are fixed.

7. Benchtop Template, Cut and Install

Laminate benchtops can often arrive with the cabinets and go on during installation. Stone works differently. The fabricator templates the tops once the base cabinets are fixed, then cuts and installs them. An undermount sink also needs its adhesive to cure before plumbing.

Typical time: same visit for laminate, about 2 to 3 weeks for stone.

Before you move on: confirm the stone install date with your fabricator.

8. Splashback, Fit Off and Handover

Tiles can go on soon after the benchtop. Glass or stone splashbacks get templated after the benchtop, which adds another wait. The plumber and electrician then connect the sink, cooktop, oven and power points.

Typical time: 2 days for tiles, up to 2 weeks for a slab splashback.

Before you move on: ask for the plumbing compliance certificate and the Certificate of Electrical Safety.

In Victoria, your electrician must issue a Certificate of Electrical Safety and your plumber a plumbing compliance certificate. Keep both with your home records.

Which Kitchen Renovation Steps Can Overlap?

The fastest jobs are not rushed. They overlap the right stages and keep the rest in strict order.

Can run at the same timeHas to wait
Design and appliance selectionCabinet drawings wait for final appliance sizes
Cabinet manufacture while you still use the old kitchenDemolition waits for a confirmed cabinet date
Stone selection while the cabinets are madeStone templating waits for fixed base cabinets
Flooring choice during designSlab splashbacks wait for the installed benchtop

The biggest saving comes from the first two rows. When cabinets are made before demolition, the kitchen is out of use only for work that must happen on site. Coordinating cabinetry and stone under one team also removes a handover between two suppliers. At Attila, our sister business Attila’s Natural Stone supplies the stone, so one team runs one schedule.

Want cabinetry and stone on one schedule?

Book a free design consultation at our Campbellfield showroom and get a date for every stage.

Flat Pack or Fully Assembled: How Each Changes the Timeline

Attila supplies both fully assembled and flat pack cabinetry, made to your measurements in Campbellfield. The choice is about who builds the boxes, and when.

Fully assembled: cabinets arrive built and ready to fix. This usually means the fewest days on site and the shortest time without a kitchen.

Flat pack: you or your installer assemble the cabinets before fitting them. It suits hands-on owners, investors and builders who manage their own trades.

If you choose flat pack kitchens, assemble the cabinets in the garage before the old kitchen comes out. That moves the assembly days off your timeline. Measure carefully, because a wrong size costs more time than any other mistake.

What Delays a Kitchen Renovation in Melbourne?

Most delays trace back to a decision made late or a fact found late.

Late design changes: moving a sink after rough-in sends the plumber and electrician back.

Appliances not on site: integrated appliances need exact model sizes before the cabinets are drawn.

Older homes: period and post-war houses often hide uneven floors, old wiring or asbestos.

Structural work: removing a wall needs a building permit, a surveyor and usually an engineer.

Apartment rules: lift bookings, set work hours and owners corporation approval all affect the start date.

Holiday shutdowns: many suppliers and trades close over Christmas and New Year, so plan around late December and January.

Our guide to the common mistakes when ordering custom cabinets covers the cabinet side.

How Long Will You Be Without a Working Kitchen?

Plan for 1 to 2 weeks with laminate benchtops and 3 to 5 weeks with stone. The longest gap is usually between cabinet installation and the stone install, when there is no sink.

A simple temporary kitchen makes those weeks easier:

  • Move the fridge and microwave to the laundry or dining room.
  • Keep a kettle, toaster and air fryer or slow cooker on a spare table.
  • Use the laundry trough for washing up.
  • Plan simple meals for the first and last weeks, when trades are busiest.

Write two dates on the calendar before demolition: the day the kitchen goes offline and the day the sink returns.

Planning a full renovation with stone?

Visit our Campbellfield showroom to see cabinet finishes and stone together, then book your free design consultation.

Kitchen Renovation Timeline FAQs

How long does a kitchen renovation take in Australia?

Most full kitchen renovations take 6 to 12 weeks from final design to handover. The kitchen itself is usually out of use for 1 to 5 weeks. Stone, layout changes and structural work add time.

A complete renovation that moves walls or services often takes 12 weeks or more from final design. Permits, engineering and builder availability set the pace. Start planning two to three months before your preferred start date.

Fixing fully assembled cabinets usually takes 1 to 3 days. Flat pack cabinets need assembly first, so allow extra time. Stone benchtops go in later, after templating.

Keep the existing layout, finalise every selection before demolition and have appliances on site early. Laminate benchtops avoid the stone templating wait. With all of that in place, the kitchen can be out of use for around 1 to 2 weeks.

A like-for-like kitchen replacement often does not need a building permit. Removing or altering a structural wall usually does, through a registered building surveyor. Licensed trades must do the plumbing and electrical work and issue compliance certificates.

Yes, most families stay at home. Set up a temporary kitchen with the fridge, a microwave and a kettle, and wash up in the laundry trough. Expect dust and noise during demolition and rough-in.

Yes, assembly adds time on site. Win it back by assembling cabinets before the old kitchen comes out, or order them fully assembled.

Plan the Timeline Before You Pick a Start Date

A realistic kitchen renovation timeline starts with decisions, not demolition. Lock in the layout, appliances and benchtop first. Then the weeks without a kitchen cover only on-site work.

Attila Kitchens designs, makes and installs cabinetry from Campbellfield. Stone from Attila’s Natural Stone runs on the same schedule. See how our kitchen renovations in Melbourne work, or walk through our design and build process step by step. Before you sign, our list of questions to ask your cabinet maker helps you compare quotes.

[hfe_template id='1897']

Attila Kitchens

Book a Free Kitchen Design Consultation

Campbellfield Showroom | 447+ Five-Star Reviews Across the Attila Group

Book Your Free Consultation

Bring your measurements and budget. We will show you what is possible.

Name

Make an enquiry